We are thrilled to share an update of the Project Love construction - 

The significant work has been making the pharmacy extension watertight, which is very close to completion and service rough in has started. Dayward is ticking along with the Joinery design approved and the joinery plinths have been installed ready for vinyl scheduled for this week.

Over the next weeks the pharmacy extension will see the current scaffolding removed and reinstated elsewhere and screw piles installed ready for the external Pharmacy stairs to be erected.  The Dayward concrete floor has had a layer of screed laid ready for the vinyl to be installed this week and from there the first coats of paint will happen. 

We look forward to sharing with you the next update!